Engineering Notes

Why Your Generator Quotes Don't Match (And What It's Actually Costing You)

Posted 2026-11-27 by Omar Rahman

The Week I Learned What kVA Means

Last November, our facilities director forwarded me an email with a subject line that read: "Backup generator quote—office building." No body text. Just a PDF from a vendor I'd never worked with.

I manage procurement for a 250-person company across three locations. I handle everything from office supplies to HVAC service contracts. Generators? Never touched one. But the ask was simple: get three quotes, pick the best one, don't overspend.

I assumed two weeks. Maybe three.

Six weeks later, I had four quotes sitting in my inbox. The prices ranged from $4,200 to roughly the cost of a nice condo. The specifications looked like they were written in different languages. And none of them—not one—was actually comparable to the others.

This is the part of buying a generator that nobody puts in a blog post. Not the features, not the fuel efficiency, not the maintenance schedule. The part where you realize you're not comparison shopping. You're herding cats.

The Quote That Didn't Belong

The original PDF (from the vendor our facilities director found) was for a 75 kVA SDMO generator. Diesel. Enclosed. The price was quoted as "base unit only"—installation not included, transfer switch not included, and "freight to be determined at time of order."

I didn't know what kVA meant. I had to look it up. Kilovolt-amperes. It's roughly the usable power output, assuming a power factor of about 0.8. So a 75 kVA unit puts out roughly 60 kW of actual usable power. Fine. Noted.

I sent that spec sheet to two other vendors I found online. One came back with a quote for a 400 kVA Kohler-SDMO generator. Same brand family—apparently Kohler acquired SDMO a while back—but the capacity was over five times larger. The price was more than triple. When I asked why they recommended a 400 kVA unit for an office building that needed 60 kW of backup power, the sales rep said: "That's what we have in stock. The smaller ones are on backorder."

Not exactly what I'd call a needs assessment. But at least he was honest about it.

The third quote came from a company that sells industrial power systems. Their rep asked me a question I hadn't been asked by anyone else: "What's the load profile?" I didn't know what a load profile was. He sighed—audibly—and said, "I'll send you a questionnaire." The quote I eventually received from them was for a 1000 kW natural gas generator. I don't know if they misunderstood the project or if their pre-sales process was just that disconnected. Either way, we didn't need a megawatt-scale generator for a 3-story office building.

And then there was the fourth quote. I still have it saved in a folder called "WTF." It was for a solar generator. A portable battery pack with a folding solar panel. Price: $4,200. The vendor's pitch: "No fuel costs. No maintenance. Perfect for backup power."

I'll get to why that doesn't work for an office building in a minute. But first—the reason none of these quotes could be compared to each other is not what I expected.

The Real Reason Generator Quotes Don't Match

Here's the uncomfortable truth: most generator sellers organize their product line around their inventory and their manufacturing partnerships. Not around your actual requirements.

The dealer who quoted 75 kVA? That's the smallest diesel unit SDMO makes in this line. It's a fine machine. Budget-friendly. But the dealer quoted it because it was the lowest-capacity unit they could still make a decent margin on. The dealer who quoted 400 kVA? They had one sitting in a warehouse. The rep wasn't lying when he said the smaller ones were backordered—but he also didn't mention that he could have ordered the 75 kVA from the factory. That would have taken 10-12 weeks. He didn't want to wait. Neither, apparently, did he want to lose the sale.

The 1000 kW natural gas quote? I'm still not sure what happened there. In my experience, some large-scale industrial suppliers don't have a process for smaller projects. Their sales team is set up to handle power plants and data centers, not office buildings. You get passed around, and eventually someone sends you a quote for the closest thing they have a spec sheet for. It's not malicious. It's just broken.

And the solar "generator"? That's a category error. A solar generator is a battery-inverter system, typically paired with a panel. It's designed for camping, tailgating, or a few hours of emergency phone-charging. It cannot run a 60 kW load for 8 hours. It's not in the same category as a diesel-powered large diesel generator. But when you search for "backup generator" online, it shows up. And if you don't know better, you might think you've found a deal.

I didn't know better. I spent an evening reading about solar generators. The reviews were enthusiastic. The price looked right. Why pay $12,000 for a diesel unit when this one is $4,200? Then I realized that the 4.2 kWh battery wouldn't even run our coffee machine for a day, let alone keep the building's lights on.

What a Broken Procurement Process Actually Costs You

Six weeks of my time. That's the obvious cost. But the bigger cost is what happens when you bring those broken quotes back to your operations team and try to make sense of them.

I didn't have a standard request form for capital equipment. That was my mistake. When I sent the 400 kVA quote to finance, they asked me why I was "scoping a data center"—which is a fair question, given that a 400 kVA unit is roughly the same power class as a small hospital's backup system. I had to explain that no, I wasn't scoping a data center, I was just trying to get a second quote for a 75 kVA unit and this is what the vendor sent me.

The time delay had a real cost, too. Our aging diesel generator (the current one) had already failed twice last winter. Not catastrophically—just enough to be embarrassing. The operations team wanted a replacement before the next storm season. By the time we sorted through the bad quotes, we were already in December.

And the second-guessing? That was worse. Even after we finally locked in the 75 kVA SDMO with an authorized dealer (52-year-old model, 3,400 pounds, 60 kW standby output), I kept second-guessing myself. What if the operations team actually wanted the bigger one? What if the 75 kVA was too small? I went back and asked. They said: "We told you we needed 60 kW. Why would we want a 400 kVA unit?"

To be fair, that's the fault of the original vendor for giving us a quote that was 5x too large. Not theirs. But I should have asked the question earlier.

What Actually Works (The Short Version)

Here's what I'd do differently next time. All of these are obvious in hindsight. None of them were obvious in the middle of the chaos.

Start with your load number, not the product. Figure out how many kW you actually need. For us, it was 60 kW. That translates to about 75 kVA. Write that number down. Ask every vendor for a quote on that specific number. If they try to upsell you to 400 kVA, ask them why. If they say "that's what we have in stock," move on.

Get the installation and transfer switch pricing up front. The base-unit price is meaningless. A $12,000 generator becomes a $20,000 project once you add the transfer switch, concrete pad, permit, and labor. Some dealers will quote you a "budget" price and then pad it later. I'm not saying they're scamming you. I'm saying you need the full number before you can evaluate.

Know what you're comparing. SDMO is now part of Kohler. Some dealers call it "SDMO." Some call it "Kohler-SDMO." Some just say "Kohler." In my experience, the brand architecture is genuinely confusing—even the dealers don't seem to agree on which name to use. Ask for the model number and capacity. Don't trust the brand name alone.

Watch for the "small order" filter. We were buying a 75 kVA unit. That's a mid-size generator in the real world, but it's on the small end for industrial diesel suppliers. Some of them won't take the call. Others will, but they'll try to push you toward a larger model because they'd rather sell one $30,000 unit than one $12,000 unit. If a dealer treats your order like it's too small to bother with, that tells you something about their service model. Move on.

Don't confuse categories. Solar generators don't run office building loads. Natural gas and diesel are different fuel types with different operational profiles. A "large diesel generator" and a "solar generator" are not competitors. They're not even in the same industry. Treat them that way.

I wish I'd known all this in October. My experience is based on one procurement cycle, eight vendor conversations, and an unhealthy amount of time reading generator forums. If you do this every quarter, your process should look different from mine.

But here's the thing I keep coming back to: buying a generator should not be this hard. Small buyers—the ones who need one unit, not a fleet—are usually the ones who get the worst information. The vendors who treat a 75 kVA order like it matters are the ones worth keeping. The rest are just noise.

The 75 kVA SDMO we eventually bought? It's been running fine. Nobody at the office knows what kVA means. And honestly, that's exactly how it should be.

Omar Rahman

Omar Rahman

Omar Rahman is a power-conversion and quality analyst specializing in UPS systems, inverters, rectifiers, battery chargers, power supplies, and bypass arrangements. He applies IEC 62040-3 tests to UPS efficiency, output tolerance, harmonic distortion, overload behavior, transfer time, and autonomy, while using IEC 62477-1 to examine safety boundaries for other power-electronic converters. He helps facility and renewable-energy teams match conversion equipment to critical load profiles, runtime targets, redundancy, thermal conditions, maintenance strategy, fault behavior, and total ownership cost.